March 31, 2016 – On Monday, April 4, street reconstruction and utility work will begin on the following streets:
Noeske - Balfour to Helen
Harrison - Noeske to Ashman
Princeton Court - Jefferson to the end of the court
These streets will be closed to thru traffic throughout the duration of the project. In addition, Ashman Street is anticipated to be reduced to one lane of traffic on Wednesday, April 6 while crews install new storm sewer at the intersection of Harrison and Ashman. Work on these streets is expected to be completed by mid- to late-June.
As this project continues, information will be posted on City of Midland Facebook and Twitter pages. Like us at facebook.com/MidlandConstruction and follow us at twitter.com/cityofmidlandmi for updates.
For more information, contact City Engineering at 989-837-3348.