Posted on: February 19, 2021

City Announces Spring/Summer 2021 Construction Schedule

Orange traffic cones on a blue sky

February 19, 2021 – The City of Midland Engineering Department is ramping up for another busy construction season in 2021 with a variety of street reconstruction, resurfacing, and water main replacement projects on this year’s list.

Planned high-traffic improvements include street reconstruction and water main replacement projects on E. Wheeler Street from Swede Avenue to US-10 and Sturgeon Avenue from N. Saginaw Road to W. Wackerly Street and a street resurfacing project on S. Saginaw Road from E. Patrick Road to Dartmouth Drive. Additional streets seeing reconstruction projects include State Street, Reardon Street, Greenbrier Terrace, Dartmouth Court, and W. St. Andrews Street from Eastman Avenue to the Midland Country Club.

In addition, a new water main installation project will take place in the Lyon/Patrick greenbelt area between E. Carpenter Street and Bayliss Street. This project does not involve street work.

The City anticipates street and lane closures during projects, and detours will be posted if necessary. A complete list of 2021 City projects and their estimated months of start and completion is below. 

For more information, contact City Engineering at 989-837-3348. Project updates will be made available during construction season at http://bit.ly/midlandroads. Residents may also receive updates on the City of Midland Facebook page at facebook.com/cityofmidlandmi, on Twitter at @CityofMidlandMI, or via the “Notify Me” feature on the City’s website at www.cityofmidlandmi.gov

 

Project

Project Limits

Project Description

Est. Start

Est. Completion

Lyon/Patrick Greenbelt Water Main

E Carpenter to Bayliss

Water Main Installation

May

July

Sturgeon Ave

N Saginaw to W Wackerly

Street Reconstruction &

Water Main Replacement

May

October

E Wheeler St

Swede to US10 Ramp

Street Reconstruction &

Water Main Replacement

May

October

Reardon St

Rodd to George

Street Reconstruction

June

August

State St

North to George

Street Reconstruction

June

August

S Saginaw Rd

E Patrick to Dartmouth

Street Resurfacing

June

August

Surface Treatment Program

Various Major & Local Streets

Crack Filling/Chip Seal/

Slurry Seal

July

September

Greenbrier Ter

Lambros to Canterbury

Street Reconstruction

July

September

Lindy St

Scott to E Ashman

Street Reconstruction

July

September

Dartmouth Ct

E St Andrews to End of Court

Street Reconstruction

July

September

Salem St

E St Andrews to E Sugnet

Street Reconstruction

July

September

Burrell Ct

Eastman to End of Court

Street Reconstruction &

Water Main Replacement

July

October

Hubbard St

W Main to W Buttles

Street Reconstruction

July

October

W St Andrews Rd

Eastman to Country Club

Street Reconstruction & Water Main Replacement

August

October

 

Facebook Twitter Email

Other News in News Carousel

Calculator with bills

Reminder: Tax Payments Due September 15

Posted on: August 27, 2021
A small, plastic green garbage can

Saturday Hours Resume at Landfill March 6

Posted on: February 19, 2021
Toy cars in a parking lot

On-street Parking: Rules of the Road

Posted on: November 6, 2020
A peaceful stream with sunlight

Keep Waterways Clean & Debris-Free

Posted on: October 1, 2020