Posted on: March 14, 2014

[ARCHIVED] City Construction Projects Planned for Spring & Summer 2014

Project Information Table

March 14, 2014 – The City of Midland Engineering Department is ramping up for a busy spring and summer, with various construction projects planned for roadways in Midland.

Major street projects that could affect citizens’ travel routes are described below. Also, a complete list of 2014 projects, including estimated start and completion dates, is provided in the table below.

Major streets scheduled to undergo street reconstruction include E. Ashman Street from Cambridge Street to Swede Avenue, Washington Street from E. Ashman Street to Patrick Road, Ellsworth Street from Ashman to George, and Rodd Street from Main to Buttles. The City anticipates street and lane closures during the projects, and detours will be posted.

A major street and utility improvement project will take place on Waldo Road from Wheeler Street to Diamond Drive. This project will install storm sewer, sanitary sewer, and water main to serve a future residential development north of the US 10 Highway.

The Airport Road Bridge over the Sturgeon Creek will be replaced, and repairs will take place on the Currie Bridge and Mark Putnam Bridge (Poseyville Road).

Street reconstruction activities will also take place on several local streets: Partridge Lane from Wackerly Street to Woodbridge Lane; Cambridge Street from St. Andrews to Boston Street; and Wallen Street from Kentwood Drive to Lancaster Street will undergo selective curb replacement, sidewalk repairs, ramp replacements, and street paving activities.

A current list of City projects and their estimated start and completion dates are included in the table attached. This same list can be found on the construction updates webpage on the City’s website. This page includes an interactive map with project information and daily updates on City of Midland construction projects that are currently in progress or planned for future dates.

As the 2014 construction season gets underway, motorists are encouraged to sign up for weekly City construction updates by subscribing to City Hall News.

For questions or further information on these projects, contact Engineering at 989-837-3348 or visit the City’s website.

Facebook Twitter Email

Other News in News Releases

Winter 2023 Tax Bills Mailing in December

Posted on: November 17, 2023

Reminders of City Parking Rules

Posted on: November 9, 2023

City to Recognize Beautification Efforts

Posted on: October 27, 2023

DPS Reminds You to Shake Your Mailbox

Posted on: October 13, 2023

Spray Parks to Close for the Season

Posted on: September 28, 2023

Pedestrian Plazas Close for the 2023 Season

Posted on: September 28, 2023

Help Keep Waterways Clean This Fall

Posted on: September 22, 2023

Remove Decorations from Midland Cemetery

Posted on: September 15, 2023

Winter 2022 Tax Payments Due Soon

Posted on: January 20, 2023

Reminder on City Snow Removal Rules

Posted on: December 9, 2022

Taglauer Named Code Official of the Year

Posted on: October 21, 2022

Reminders of City Signage Ordinance

Posted on: October 7, 2022

City Promotes John Jurek to Fire Marshal

Posted on: September 2, 2022

Lacey Todd Promoted to City Clerk

Posted on: April 8, 2022

MPD Awarded Grant for 3D Scene Scanner

Posted on: January 7, 2022